Sabiha Gökçen Airport Project

Sabiha Gökçen Airport Project

Sabiha Gökçen Airport 2nd Runway Construction 2nd Phase Supplement Works

Airport Fuel Hydrant system construction works at Sabiha Gökçen Airport was tendered to MEP Industrial by KMC Partnership at the beginning of 2020.

Within the scope of the project, the following works were carried out:

  • Supply of 17,126 m underground jet fuel pipeline with different diameters such as 20”, 14”, 12”, 8”, 6” and installation works with 100% NDT control,
  • Supply and installation of 127 number Cavotec-Dabico type fuel hydrant pits and 24 number High point/ Low point drain pits according to World Civil Aviation rules,
  • Construction works of 9 number valve rooms within the scope of construction works. Supply & installation of valve chamber covers and Vent/Drain pits according to World Civil Aviation rules.
  • Supply & installation of 45 number various diameters DBB Valves and actuators.
  • Supply & installation of all 2 number 350 m³/h capacity Fuel Pumps, 2 number Filter/Water Separator, Gate/Check/Ball Valves, Filters, Compensators etc. along with piping works addition to existing system.
  • Construction of all civil works including excavation & backfill for valve rooms and all underground systems.
  • Supply & installation of all electrical-electronic systems required for Valve Rooms.
  • Completion of Fuel Hydrant System Pneumatic, Hydrostatic and Flushing tests processes.
  • Supply & installation of all materials, instruments and electrical instrument works for Leakage Detection System (LDS), Emergency Stop System (ESD), Cathodic Protection System etc. to be able to managed from electrical control room.